The Grande Dixence Dam is a massive concrete gravity dam located in the Valais canton of Switzerland.

Grande Dixence Staumauer
Grande Dixence Staumauer

As a gravity dam, it uses its immense weight to hold back the massive pressure of the water behind it. It sits on the Dixence river at the head of the Val d'Hérémence. This structure is a vital part of the Cleuson-Dixence Complex. Currently, it holds the title of the tallest gravity dam in the world. It is also the tallest dam in Europe and the seventh tallest dam overall. The dam creates a large reservoir known as Lac des Dix, which is the largest lake in the Alps located above 2,000 meters altitude.

The system works by capturing and moving water to generate hydroelectric power. Most of the water in the reservoir comes from glaciers melting during the summer months. To keep the reservoir full, four different pumping stations—Z’Mutt, Stafel, Ferpècle, and Arolla—transport water through 10-kilometer-long tunnels.

Installations hydroélectriques de la Grande Dixence
Installations hydroélectriques de la Grande Dixence

Once the water is stored, it is released through three large pipes called penstocks. These penstocks carry the water down to four different power stations: Chandoline, Fionnay, Nendaz, and Bieudron. Inside these stations, the rushing water spins Pelton turbines, which are machines designed to capture energy from high-pressure water jets. This process converts the movement of the water into electricity.

The Cleuson-Dixence Complex consists of several distinct parts that work together. The primary dam holds the Lac des Dix, which has a surface area of 4 square kilometers. At its peak capacity, the reservoir contains approximately 200 million cubic meters of water. The depths of the lake can reach up to 240 meters. The system also includes the Cleuson Dam to the northwest, which sends water from its own reservoir, Lac de Cleuson, into the main system. While the complex moves water between different reservoirs, it is not technically classified as a pumped-storage scheme.

The history of this site began in 1922 with the establishment of Energie Ouest Suisse (EOS). The company sought to use the water from Switzerland's many glaciers to create electricity. In 1929, EOS acquired the license for the upper Dixence basin and began building a smaller dam. This first dam was completed in 1935 and supplied the Chandoline Power Station. However, as industries grew after the Second World War, a much larger project was needed. Construction on the current Super Dixence Dam began in late 1950.

ETH-BIB-Grande Dixence, Staumauer (Hérémence)-LBS H1-018840
ETH-BIB-Grande Dixence, Staumauer (Hérémence)-LBS H1-018840

By 1961, 3,000 workers had finished pouring the concrete. The original 1935 dam was eventually submerged by the rising waters of the new reservoir.

Engineering details make the dam a remarkable feat of construction. The dam is wide at both its base and its crest, which reaches an altitude of 2,475 meters. It contains approximately 365 million cubic meters of concrete. To ensure the structure stays secure, engineers used a grout curtain. This is a deep layer of material that surrounds the dam and reaches 100 meters into the foundation. It extends on each side of the valley to anchor the dam to the ground. When the dam was finished, it stood 285 meters high. It held the record for the world's tallest dam until 1972, when the Nurek Dam in Tajikistan reached 300 meters.

The power stations within the complex vary in size and capability. The Chandoline Power Station is the smallest, using five Pelton turbines to produce 50 MW. The Fionnay Power Station is larger and receives water through a tunnel with a 10% gradient. After passing through a surge chamber, the water enters a penstock with a steep 73% gradient. This water spins six Pelton turbines to generate 110 MW. The Nendaz Power Station is the second-largest in Switzerland. It uses six Pelton turbines to produce 150 MW.

Installations hydroélectriques de la Grande Dixence
Installations hydroélectriques de la Grande Dixence

Finally, the Bieudron Power Station is a massive facility that generates 425 MW.

The Bieudron Power Station is particularly significant for its technical achievements. It was built by Grande Dixence SA and EOS between 1993 and 1998 at a cost of US$1.2 billion. This station holds three world records related to its immense power output. These include the height of its head, the output of each individual Pelton turbine, and the output per pole of its generators. Although a penstock rupture caused it to stop working in 2000, it became partially operational in 2009 and fully operational in 2010. The entire complex is incredibly productive, generating about 2,000 GWh of electricity annually. This is enough to power approximately 400,000 Swiss households.

This massive project connects several different fields of science and engineering. It combines hydrology, the study of how water moves, with civil engineering to build the dam. It also relies on physics to turn the kinetic energy of falling water into electrical energy. The seasonal cycle of the glaciers provides a natural rhythm to the electricity production. The reservoir is usually at its highest in late September and reaches its lowest point around April. By managing these natural resources, the Grande Dixence Dam serves as a giant, controlled engine for the region.

849 words

Where will your curiosity go next?

Keep exploring at your chosen reading level.

🖼️ Images & Media (3)
ETH-BIB-Grande Dixence, Staumauer...
File:Grande Dixence Staumauer.jpg
Grande Dixence Staumauer.jpg
File:Installations hydroélectriques de la Grande Dixence.svg
Installations hydroélectriques de la...
More to explore

🔬 Go deeper

More advanced topics to explore

🪜 Step back

Simpler topics to build understanding

What is Nepedia?

A free, ad-free encyclopedia for children. Every article is written at five reading levels, so the same page works for a five-year-old and a fifteen-year-old — use the level switcher above to see this one change. No account needed to read.